CONSTRUCTION ON SOUTHBOUND SR-36 RESUMES

Starting as early as Monday, Feb. 3, crews will resume construction to widen southbound State Route (SR) 36 to three lanes between Sunset Road and Stansbury Parkway in Tooele County. Construction is anticipated to continue through summer 2025.

WHAT TO EXPECT:

  • Daywork Monday – Saturday from 7 a.m. to 6 p.m.
  • Daytime lane closures until 1 p.m., as needed
  • Minor travel delays
  • Increased noise, dust, and vibration

Construction schedules are weather-dependent and subject to change.


For additional project information and to learn about upcoming construction on northbound SR-36, visit our website.

HOTLINE
(385) 324-2122
EMAIL
[email protected]
WEBSITE
udotinput.utah.gov/sr36andI80improved

We’re making significant progress on the SR-201 Over 3200 West Bridge Rehabilitation Project, and we appreciate your patience as we move into the next phase of work.

Upcoming Ramp Traffic Switches & New Configuration

  • Eastbound SR-201 Ramp Traffic Switch: Friday, February 7, at 7 a.m.

  • Westbound SR-201 Ramp Traffic Switch: Monday, February 10, at 7 a.m.

New Traffic Configuration:

  • Lane Narrowing & Traffic Shift: Lanes will be shifted outward, away from the bridge, to allow crews to work safely on the shoulders.

  • Barrier Relocation & Stripe Removal: Crews will adjust barriers and remove old striping to accommodate the new configuration.

  • Increased Truck Activity: Trucks will be entering and exiting the work zone—please slow down and stay alert.

  • Work Progression: Crews will begin work on the SR-201 eastbound off-ramp, followed by the westbound on-ramp later in the week.

3200 West Reconstruction – Work Under the Bridge

With traffic now shifted back onto the new bridge deck, crews are focusing on rebuilding 3200 West underneath SR-201. This work is necessary before the intersection can fully reopen to traffic on February 21.

Here’s what’s happening:
Installing new traffic signals
Replacing curb & gutter along the roadway and surrounding medians
Restoring signage that was temporarily removed
Placing new striping with white and yellow lane markings and directional arrows
Removing temporary concrete barriers to restore the roadway

What’s Next?

Even after 3200 West reopens, additional work will continue in the area, including:

  • Grading and stabilizing slopes

  • Upgrading signal and Intelligent Transportation Systems – traffic cameras, sensors and signal coordination to improve traffic flow and safety

  • Adding and enhancing – Shared-Use Path, sidewalks and accessible access ramp improvements

Some work that requires warmer temperatures will take place later this spring, including:

  • Placing a polymer overlay on the bridge deck

  • Painting the girders and concrete

  • Paving island areas

  • Seeding slopes for erosion control

Watch the latest progress update HERE.

We appreciate your patience and support as we work toward a safer, more efficient 3200 West intersection. If you have any questions, feel free to reach out.

Know before you go. Check UDOT Traffic before hitting the road.

Thank you for helping us keep the work zone safe!

For more updates and detour information:
udotinput.utah.gov/SR201Bridge.